When an Operator with operations in Africa faced the challenge of re-establishing well barriers for a multi-well plug and abandonment (P&A) campaign, they turned to us for well control expertise. With a focus on mitigating the risks of compromised barriers and potential well control issues, we delivered tailored well control strategies and solutions to ensure a safe and successful outcome.

Project Highlights

Client: Global Energy Company

Asset: Gas field, Mozambique

Work executed: Autumn 2024

Project Introduction

Our Well Control experts provided consultancy during the planning and preparation of a plug and abandonment (P&A) campaign on multiple wells in a gas field located in Mozambique. The scope included addressing wells with compromised barrier integrity, which had resulted in pressure build-up and gas presence at the surface.

Client challenges

Our client trusted us with planning for their upcoming multi-well P&A campaign to provide advisory services focused on re-establishing well barriers. This involved removing compromised barriers, a critical operation with a risk of losing control in offshore wells. Our team analysed and simulated various well control scenarios, evaluated mitigation options, and developed well control strategies to ensure the P&A campaign’s safety and success.

Our solutions

  • Reviewed upcoming operations and conducted detailed risk assessments.
  • Predicted potential drilling outcomes to prepare for various scenarios.
  • Analyzed worst-case events and developed comprehensive blowout contingency plans.

The results

  • Raised awareness of planned high-risk operations.
  • Assisted in selecting the optimal approach for safe P&A campaign execution.
  • Prepared robust blowout contingency plans to address potential challenges.

Our value

Our well control team’s involvement ensured that the P&A operations were designed and executed with a focus on safety and the effective restoration of well integrity.

I’d like to thank you once again for a very comprehensive and professional report.